News
The possibility that an idle, unconnected transmission line somehow reengerized on Jan. 7 is now "a leading hypothesis" for ...
Southern California Edison changed how crews ground idle transmission towers just days after the Eaton fire, but they won't ...
Southern California Edison is echoing calls from homeowners to move spark-prone electrical equipment underground. Company ...
(Reuters) -Southern California Edison (SCE), a subsidiary of utility Edison International, said on Friday it had submitted an ...
1don MSN
Southern California Edison has announced that it will bury more than 150 miles of power lines in in Altadena and Malibu ...
SCE said funding sources are still needed to cover the estimated $860 million to $925 million cost to place 153 circuit miles ...
The company — and perhaps its ratepayers — also face potential high costs from numerous lawsuits alleging live power lines ...
Weeks after deadly fires swept through Los Angeles County, the state regulator in charge of overseeing utility companies declined a request that would have required California’s largest utilities to ...
Edison International's Southern California division plans to rebuild electrical distribution infrastructure affected by wildfires in January for $860 million to $925 million. Southern California ...
Southern California Edison Provides Rebuilding Plan for Electric Distribution in Altadena and Malibu
Southern California Edison today provided an initial comprehensive plan to rebuild the impacted electrical distribution ...
Southern California Edison Lays Out $925 Million Plan to Rebuild ... and towers in Altadena started one of the blazes - the Eaton Fire. SCE has also been sued by the LA County and the City of ...